Building Safety Act: gateways and timescales
Hard-stop gateways for higher-risk buildings remain a critical-path risk. Know the statutory periods and what actually happens.
- Higher-risk building: at least 18 m or 7 storeys, with at least two residential units.
- Gateway 2 (before work starts): statutory period 12 weeks for a new HRB, 8 weeks for work to an existing HRB. Decisions have often taken far longer; allow a realistic programme margin.
- Major changes during construction need BSR approval (6 weeks); notifiable changes must be notified before the work is done.
- Gateway 3 (before occupation): statutory period 8 weeks. Occupying before the completion certificate and registration is a criminal offence.
Why it matters to a PM: design maturity before Gateway 2, change control after approval, and Gateway 3 in the handover programme.